Esnek robotik hücrelerde çoklu parça tipi çizelgelemesi

2009
0 views
0 downloads
Advisor: Doç. Dr. Oya Ekin Karaşan

Abstract (EN)

This thesis considers the scheduling problem arising in two-machine manufacturing cells which repeatedly produce a set of multiple part-types, and where transportation of the parts between the machines is performed by a robot. the cycle time of the cell depends on the robot move sequence as well as the processing times of the parts on the machines. for highly flexible cnc machines, the processing times can be adjusted. as a result, this study tries to find the robot move sequence as well the processing times of the parts on each machine that minimize the cycle time. the problem of determining the best cycle in a 2-machine cell is first modeled as a travelling salesman problem. then an efficient 2-stage heuristic algorithm is constructed and compared with the most common heuristic approach of longest processing time.

Author

Dr. Gül Didem Batur

How to Cite

Gül Didem Batur (Master Thesis). Esnek robotik hücrelerde çoklu parça tipi çizelgelemesi, 2009, Bilkent University, Endüstri Mühendisliği Bölümü.

Keywords

License

Tüm Hakları Saklıdır

This work is shared under the specified license terms.

More theses from Bilkent University