Kontrol edilebilir işlem süreleriyle paralel makinalarda yeniden çizelgeleme
2012
0 views
0 downloads
Advisor: Prof. Dr. M. Selim Aktürk
Abstract (EN)
In many manufacturing environments, the production does not always endure as it is planned. Many times, it is interrupted by a disruption such as machine breakdown, power loss, etc. In our problem, we are given an original production schedule in a non-identical parallel machine environment and we assume that one of the machines is disrupted at time t.Our aim is to revise the schedule, although there are some restrictions that should be considered while creating the revised schedule. Disrupted machine is unavailable for a certain time. New schedule has to satisfy the maximum completion time constraint of each machine. Furthermore, when we revise the schedule we have to satisfy the constraint that the revised start time of a job cannot be earlier than its original start time. Because, we assume that jobs arenot ready before their original start times in the revised schedule.Therefore, we have to find an alternative solution to decrease the negative impacts of this disruption as much as possible. One way to process a disrupted job in the revised schedule is to reallocate the job to another machine. The other way is to keep the disrupted job at its original machine, but to delay its start time after the end time of the disruption. Since the machines might be fully utilized originally, we may have to compress some of the processing times in order to add a new job to a machine or to reallocate the jobs after the disruption ends.Consequently, we assume that the processing times are controllable within the given lower and upper bounds.Our first objective is to minimize the sum of reallocation and nonlinear compression costs. Besides, it is important to deliver the orders on time, not earlier or later than they are promised. Therefore, we try to maintain the original completiontimes as much as possible. So, the second objective is to minimize the total absolute deviations of the completion times in the revised schedule from the original completion times.We developed a bi-criteria non-linear mathematical model to solve this nonidentical parallel machine rescheduling problem. Since we have two objectives, we handled the second objective by giving it an upper bound and adding this bound as a constraint to the problem. By utilizing the second order cone programming, we solved this mixed-integer nonlinear mathematical model using a commercial MIP solver such as CPLEX. We also propose a decision tree based heuristic algorithm. Our algorithm generates a set of solutions for a problem instance and we test the solution quality of the algorithm solving same problem instances by the mathematical model. According to our computational experiments, theproposed heuristic approach could obtain close solutions for the first objective for a given upper bound on the second objective.
Author
Dr. Müge Muhafız
How to Cite
Müge Muhafız (Master Thesis). Kontrol edilebilir işlem süreleriyle paralel makinalarda yeniden çizelgeleme, 2012, Bilkent University.
Keywords
License
Tüm Hakları Saklıdır
This work is shared under the specified license terms.
More theses from Bilkent University
- Geç Antik Çağ'da Aşağı Tuna: Histria örneği(2023)
- Petrol fiyatları ve getiri eğrisi(2024)
- Sözle yönlendirme üzerine makaleler(2014)
- İletişim ağları ve sağlık uygulamaları için çok kollu haydut algoritmaları(2022)
- Türk Anayasa Mahkemesinin içtihatları ışığında karşılaştırmalı anayasal mutluluk(2023)
- Doğrusal karbon zincirlerinin yoğunluk fonksiyoneli teorisi ile incelenmesi(2023)
