Planning of relocation of belt distribution center project using CPM the EÜAŞ/AEL
Is this your thesis?
This record came from a bulk archive import. If it’s yours, link it to your profile.
Abstract (EN)
Relocation activities of belt distribution point in Afşin ? Elbistan, Kışlaköy open cast mine (EÜAŞ) was analyzed using Critical Path Method (CPM). New belt distribution point consists of 6 belt conveyor lines comes from excavating site of the mine, 5 belt conveyor lines comes from dumping area and 2 belt conveyor lines go to coal stock pile. All the activities necessary to relocate belt distribution point is identified and the activities take place on the critical path were determined. Totally, 483 working days are needed to complete the project and any delay on these activities cause to extend project completion time. Key Words: Critical Path Method, Project Management, Open Cast Mine, Kışlaköy
Author
Mustafa Güneş
How to Cite
Mustafa Güneş (Master Thesis). Planning of relocation of belt distribution center project using CPM the EÜAŞ/AEL, 2007, Çukurova University.
Keywords
License
Tüm Hakları Saklıdır
This work is shared under the specified license terms.
More theses from Çukurova University
- An investigation of violent and nonviolent adolescent' families in terms in terms of family fuctioning, anger and anger expression(2006)
- Adolescents who have single parents family and full family were compared in respect to their life satisfaction and quality of life(2009)
- 9mm. identifying cartridge cases and bullets obtained from firearms and detection of brands(2020)
- Assessing morphological and genetic diversity among traditional African eggplant landraces and detecting salt tolerance and anther culture performance of selected accessions(2022)
- The effects of collaborative video-blog projects on Turkish EFL students' linguistic and digital literacy skills(2025)
- Cultural significance in foreign learning and teaching with special emphasis on reading comprehension through cultural schemata(1992)